Warmly celebrate the successful completion of pile driving for the main berth of the new KOT project at Mombasa Port by HaiZhong Steel Pipe.


Release time:

2020-08-21

On August 7, local time, the driving of steel pipe piles for the main berth of the newly built KOT project at Mombasa Port was successfully completed.

Warmly celebrate the successful completion of pile driving for the main berth of the new KOT project at Mombasa Port by HaiZhong Steel Pipe.

 

On August 7, local time, the driving of steel pipe piles for the main berth of the newly built KOT project at Mombasa Port was successfully completed.

The main berth of the KOT project features an offshore, high-pile, cast-in-place pier structure. The total length of the wharf is 770 m, comprising four berths and a total of 417 steel pipe piles—290 inclined piles and 127 vertical piles. All steel pipe piles were fabricated at the Laem Chabang Steel Pipe Plant by Zhuhai Haihong Steel Pipe Co., Ltd.

During production, despite the dual challenges of the pandemic and adverse weather conditions, we optimized pipe fabrication schedules and maintained rigorous quality control. The bearing capacity of the steel pipe pile foundations at the main wharf fully met design specifications, laying a solid foundation for subsequent streamlined construction of piers and abutments.

 

 

The COVID-19 situation in Kenya is severe, but Hai Chong Ren has proactively addressed challenges at every stage, successfully coordinating with the project team to fabricate and transport 12 barges of steel pipe piles, thereby ensuring the smooth completion of pile driving for the main wharf’s foundation.

 