The Lekki Port Project in Nigeria successfully completed all the front wall piles
Release Time:
2022-06-23
The front wall of the container berth in this project adopts tube-sheet composite piles, with a maximum diameter of 2.3 meters and a pile length of 41 meters. This project has high requirements on the pile position, verticality and lock offset accuracy. There is a hard soil layer with a standard penetration rate of 50-150 hits on the surface layer. Sand leakage risk.

The front wall of the container berth in this project adopts tube-sheet composite piles, with a maximum diameter of 2.3 meters and a pile length of 41 meters. This project has high requirements on the pile position, verticality and lock offset accuracy. There is a hard soil layer with a standard penetration rate of 50-150 hits on the surface layer. Sand leakage risk.
In the face of difficulties, the General Manager Department of the Lekki Port Project prepared to build a steel pipe pile manufacturing plant, introduced a double-wire automatic submerged arc welding process production line from Zhuhai Haizhong Steel Pipe Co., Ltd. Steel pipe pile production quality and supply capacity. At the same time, a technical team was formed to develop a double positioning device of "steel casing + positioning frame", which achieved the pile driving accuracy higher than the design requirements, and ensured the smooth construction of the tube-sheet combined pile, and it was 15 days ahead of schedule. Finish.
At present, the overall construction progress of the project has been completed 60%, and all the front wall piles have been successfully completed, laying a solid foundation for the project to be completed on time.
Related News